Apartments E1 - Backfilling final layer

Apartments E1 - Final floor slab progress

Apartments E1 - Total progress

Apartments E2 - Ground floor slab

Apartments E2 - Total progress

Apartments E3 - Final floor concrete pouring

Apartments E3 - Final floor slab progress

Apartments E3 - Total progress

Apartments E - Total progress

Apartments F4 - First floor slab progress

Apartments F4 - Total progress

Apartments F5 - Total progress

Apartments F6 - Backfilling between foundations

Apartments F6 - First floor slab concrete pouring

Apartments F6 - Total progress

Apartments F - Total progress

Apartments G7 - Backfilling between foundations

Apartments G7 - Total progress

Fence - Landscape layout progress

Shopping Mall - Elevation 2 General progress

Shopping Malls - Elevation 2 General progress

Suites A7 - Final floor slab formwork progress

Suites A7 - Total progress

Suites A7 B6 C10 and D14 - Roof pergolla concrete casting

Suites A7 B6 C10 and D14 - Roof pergolla general layout

Suites B6 - Total progress

Suites C10 - Total progress

Suites D14 - Final floor slab concrete casting

Suites D14 - Total progress

Water Tank - Cover slab outer moisture insulation test

Water Tank - Inner side insulation materials sample

Water Tank - Inner side insulation preparation

Zone 3 Services Area - General progress